QUOTECHECKER.NET

QuoteRadar

88% of quotes have no change-order clause

We ran 7,810 real construction and renovation quotes through our analysis. The single most conflict-prone item — how extra work gets priced and approved — was missing from 88 out of every 100. And that is not the only structural blind spot.

The figures below come from our own anonymised analysis of 6,704 quotes with a readable terms section. They show how often an essential clause or line item is missing. This is about the structure and completeness of quotes — not about price levels — and no individual quote, company or amount is ever shown.

Money & scope

88%

missing in 88% of quotes

Change-order / extra-work rule

How extra work is priced and approved — the top source of disputes.

37%

missing in 37% of quotes

Explicit exclusions list

Without a "not included" list, the scope boundary is vague — and that is where extra costs are born.

44%

missing in 44% of quotes

"Provided by client" section

Power, water, access, decisions: what you must arrange yourself.

24%

missing in 24% of quotes

Staged payment schedule

How payments track the actual progress of the work.

13%

missing in 13% of quotes

Payment terms

When and how you pay — the most commonly covered item, yet still missing in some quotes.

Risk & liability

25%

missing in 25% of quotes

Liability clause

What the contractor is (not) liable for — essential to know before signing.

29%

missing in 29% of quotes

Construction insurance (CAR)

Who insures the work while it is being built.

28%

missing in 28% of quotes

Environmental / asbestos exclusion

A real cost risk in older buildings; an exclusion should at least be stated.

30%

missing in 30% of quotes

Permits responsibility

Who applies and who pays the fees — or it surfaces later as a surprise.

16%

missing in 16% of quotes

Applicable terms & conditions

Which general conditions govern the deal.

Process & timing

27%

missing in 27% of quotes

Work starts only after written order

Protects both sides: no work without a confirmed order.

18%

missing in 18% of quotes

Quote validity period

How long the offer stands.

32%

missing in 32% of quotes

Ownership of drawings/designs

Relevant if you ever switch contractors.

What this tells you

Most quotes get the basics right — payment, validity, conditions. Where they fail is on the items that only start costing money during or after the work: the change-order rule, the exclusions list, and what you must provide yourself. Exactly the silences a proper quote check exposes before you sign.

Check your own quote →

The corpus consists mostly of quotes issued to business clients; because we measure whether clauses are present (structure, not price), the pattern is broadly recognisable, though a quote to a private client may differ.

Source: our own anonymised analysis of 6,704 construction and renovation quotes (of 7,810 analysed in total), reference date Q3 2026. Figures are aggregated frequencies only; no individual quotes, companies or amounts. Completeness of clauses is structural and not tied to any single country or currency.